Binghatti Nova at JVC

Construction progress

Binghatti Nova at JVC construction updates

JVC · Binghatti Developers Fze

CompletedLast site inspection December 21, 2023 · 3 years ago
100%complete

DLD first inspected the site on Oct 25, 2022 at 1.6% complete, and recorded it as finished after 4 inspections, the last on Dec 21, 2023.

First inspection · 1.6%Latest · 100%
Construction started
September 15, 2022
Completion date registered with DLD
October 31, 2023
Site inspections
4
Units
211
Escrow bank
Sharjah Islamic Bank
DLD project no.
2494

Latest site photos

December 21, 2023

Progress over time

Progress over time
0%25%50%75%100%2023

Inspection history

  1. December 21, 2023

    4 months after the previous inspection

    +11.9%100%
  2. August 30, 2023

    5 months after the previous inspection

    +55.1%88.1%
  3. April 10, 2023

    5 months after the previous inspection

    +31.5%33%
  4. October 25, 2022

    First inspection

    1.6%

Thinking about Binghatti Nova at JVC?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2494), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.