Binghatti Hills at Dubai Science Park

Construction progress

Binghatti Hills at Dubai Science Park construction updates

Dubai Science Park · Binghatti Developers Fze

Under constructionLast site inspection July 24, 2026 · 3 months ago
90%complete

When DLD first inspected the site on Apr 22, 2024, it was 0% complete. After 3 inspections it now stands at 90%.

That is about 3.3% more of the building completed each month on average.

First inspection · 0%Latest · 90%
Construction started
April 1, 2024
Site inspections
3
Units
1,701
Buildings
2
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
3053

Latest site photos

July 24, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. July 24, 2026

    18 months after the previous inspection

    +65%90%
  2. January 10, 2025

    9 months after the previous inspection

    +25%25%
  3. April 22, 2024

    First inspection

    0%

Thinking about Binghatti Hills at Dubai Science Park?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3053), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat