Binghatti Heights at JVC Dubai

Construction progress

Binghatti Heights at JVC Dubai construction updates

JVC · Binghatti Developers Fze

CompletedLast site inspection January 9, 2024 · 3 years ago
100%complete

DLD first inspected the site on Dec 12, 2022 at 21.2% complete, and recorded it as finished after 3 inspections, the last on Jan 9, 2024.

First inspection · 21.2%Latest · 100%
Construction started
June 13, 2022
Completion date registered with DLD
August 15, 2023
Site inspections
3
Units
366
Escrow bank
Sharjah Islamic Bank
DLD project no.
2415

Latest site photos

January 9, 2024

Progress over time

Progress over time
0%25%50%75%100%20232024

Inspection history

  1. January 9, 2024

    8 months after the previous inspection

    +49%100%
  2. May 25, 2023

    5 months after the previous inspection

    +29.8%51%
  3. December 12, 2022

    First inspection

    21.2%

Thinking about Binghatti Heights at JVC Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2415), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.