Binghatti Haven at Dubai Sports City

Construction progress

Binghatti Haven at Dubai Sports City construction updates

Sports City Dubai · Binghatti Developers Fze

Under constructionLast site inspection May 7, 2026 · 6 months ago
76.1%complete

When DLD first inspected the site on Dec 24, 2024, it was 9.6% complete. After 3 inspections it now stands at 76.1%.

That is about 4.1% more of the building completed each month on average.

First inspection · 9.6%Latest · 76.1%
Construction started
December 17, 2024
Completion date registered with DLD
March 31, 2026
Site inspections
3
Units
501
Escrow bank
Abu Dhabi Islamic Bank
DLD project no.
3442

Latest site photos

May 7, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. May 7, 2026

    17 days after the previous inspection

    +1.9%76.1%
  2. April 20, 2026

    16 months after the previous inspection

    +64.7%74.3%
  3. December 24, 2024

    First inspection

    9.6%

Thinking about Binghatti Haven at Dubai Sports City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3442), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.