Binghatti Grove at JVC, Dubai

Construction progress

Binghatti Grove at JVC, Dubai construction updates

JVC · Binghatti Developers Fze

CompletedLast site inspection September 28, 2026 · 40 days ago
100%complete

DLD first inspected the site on Sep 26, 2024 at 0% complete, and recorded it as finished after 4 inspections, the last on Sep 28, 2026.

First inspection · 0%Latest · 100%
Construction started
October 1, 2024
Completion date registered with DLD
March 31, 2026
Site inspections
4
Units
404
Escrow bank
United Arab Bank
DLD project no.
3314

Latest site photos

September 28, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. September 28, 2026

    5 months after the previous inspection

    +16%100%
  2. May 14, 2026

    9 months after the previous inspection

    +57%84%
  3. July 30, 2025

    10 months after the previous inspection

    +27%27%
  4. September 26, 2024

    First inspection

    0%

Thinking about Binghatti Grove at JVC, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3314), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat