Binghatti Ghost at Al Jaddaf, Dubai

Construction progress

Binghatti Ghost at Al Jaddaf, Dubai construction updates

Al Jaddaf · Binghatti Developers Fze

CompletedLast site inspection September 21, 2026 · 2 months ago
100%complete

DLD first inspected the site on Jul 23, 2024 at 0% complete, and recorded it as finished after 5 inspections, the last on Sep 21, 2026.

First inspection · 0%Latest · 100%
Construction started
July 31, 2024
Completion date registered with DLD
March 31, 2026
Site inspections
5
Units
785
Escrow bank
Abu Dhabi Islamic Bank
DLD project no.
3192

Latest site photos

September 21, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. September 21, 2026

    42 days after the previous inspection

    +1.1%100%
  2. August 10, 2026

    8 months after the previous inspection

    +31.1%98.9%
  3. December 15, 2025

    7 months after the previous inspection

    +35.6%67.9%
  4. May 5, 2025

    9 months after the previous inspection

    +32.3%32.3%
  5. July 23, 2024

    First inspection

    0%

Thinking about Binghatti Ghost at Al Jaddaf, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3192), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.