Binghatti Crescent at JVC dubai

Construction progress

Binghatti Crescent at JVC dubai construction updates

JVC · Binghatti Developers Fze

CompletedLast site inspection October 26, 2023 · 3 years ago
100%complete

DLD first inspected the site on Dec 23, 2022 at 0.4% complete, and recorded it as finished after 3 inspections, the last on Oct 26, 2023.

First inspection · 0.4%Latest · 100%
Construction started
October 15, 2022
Completion date registered with DLD
October 26, 2023
Site inspections
3
Units
170
Escrow bank
Sharjah Islamic Bank
DLD project no.
2535

Latest site photos

October 26, 2023

Progress over time

Progress over time
0%25%50%75%100%2023

Inspection history

  1. October 26, 2023

    7 months after the previous inspection

    +59.9%100%
  2. April 10, 2023

    4 months after the previous inspection

    +39.7%40.1%
  3. December 23, 2022

    First inspection

    0.4%

Thinking about Binghatti Crescent at JVC dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2535), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat