Binghatti Corner at JVC Dubai

Construction progress

Binghatti Corner at JVC Dubai construction updates

JVC · Binghatti Developers Fze

CompletedLast site inspection August 5, 2024 · 2 years ago
100%complete

DLD first inspected the site on Nov 21, 2022 at 0% complete, and recorded it as finished after 3 inspections, the last on Aug 5, 2024.

First inspection · 0%Latest · 100%
Construction started
October 1, 2022
Completion date registered with DLD
March 31, 2024
Site inspections
3
Units
727
Escrow bank
Sharjah Islamic Bank
DLD project no.
2478

Latest site photos

August 5, 2024

Progress over time

Progress over time
0%25%50%75%100%20232024

Inspection history

  1. August 5, 2024

    14 months after the previous inspection

    +72.1%100%
  2. June 7, 2023

    7 months after the previous inspection

    +27.9%27.9%
  3. November 21, 2022

    First inspection

    0%

Thinking about Binghatti Corner at JVC Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2478), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.