Binghatti Canal at Business Bay

Construction progress

Binghatti Canal at Business Bay construction updates

Business Bay · Binghatti Developers Fze

CompletedLast site inspection June 21, 2023 · 3 years ago
100%complete

DLD first inspected the site on Apr 21, 2022 at 10.7% complete, and recorded it as finished after 4 inspections, the last on Jun 21, 2023.

First inspection · 10.7%Latest · 100%
Construction started
January 28, 2022
Completion date registered with DLD
June 30, 2023
Site inspections
4
Units
306
Escrow bank
Sharjah Islamic Bank
DLD project no.
2366

Latest site photos

June 21, 2023

Progress over time

Progress over time
0%25%50%75%100%2023

Inspection history

  1. June 21, 2023

    30 days after the previous inspection

    +1.3%100%
  2. May 22, 2023

    8 months after the previous inspection

    +42.6%98.7%
  3. September 29, 2022

    5 months after the previous inspection

    +45.4%56%
  4. April 21, 2022

    First inspection

    10.7%

Thinking about Binghatti Canal at Business Bay?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2366), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.