Binghatti Amberhall At JVC Dubai

Construction progress

Binghatti Amberhall At JVC Dubai construction updates

JVC · Binghatti Developers Fze

Under constructionLast site inspection October 26, 2026 · 12 days ago
70%complete

When DLD first inspected the site on Feb 11, 2025, it was 0% complete. After 3 inspections it now stands at 70%.

That is about 3.4% more of the building completed each month on average.

First inspection · 0%Latest · 70%
Construction started
February 15, 2025
Completion date registered with DLD
February 28, 2026
Site inspections
3
Units
710
Buildings
3
Escrow bank
United Arab Bank
DLD project no.
3552

Latest site photos

October 26, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. October 26, 2026

    6 months after the previous inspection

    +32%70%
  2. April 30, 2026

    15 months after the previous inspection

    +38%38%
  3. February 11, 2025

    First inspection

    0%

Thinking about Binghatti Amberhall At JVC Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3552), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.