Berkeley Square by Prestige One at JVC, Dubai

Construction progress

Berkeley Square by Prestige One at JVC, Dubai construction updates

JVC · Prestige Luxe Real Estate Development L.L.C

Under constructionLast site inspection September 24, 2026 · 44 days ago
3%complete

When DLD first inspected the site on Jun 26, 2025, it was 0% complete. After 4 inspections it now stands at 3%.

That is about 0.2% more of the building completed each month on average.

First inspection · 0%Latest · 3%
Construction started
July 1, 2025
Completion date registered with DLD
March 30, 2028
Site inspections
4
Units
241
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
3847

Latest site photos

September 24, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. September 24, 2026

    3 months after the previous inspection

    3%
  2. June 25, 2026

    7 months after the previous inspection

    +3%3%
  3. November 21, 2025

    5 months after the previous inspection

    +0%0%
  4. June 26, 2025

    First inspection

    0%

Thinking about Berkeley Square by Prestige One at JVC, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3847), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat