Berkeley Place at Meydan by Ellington

Construction progress

Berkeley Place at Meydan by Ellington construction updates

Mohammad Bin Rashid City · Ellington Properties Development L.L.C

CompletedLast site inspection December 24, 2024 · 2 years ago
100%complete

DLD first inspected the site on Jan 2, 2023 at 6.9% complete, and recorded it as finished after 6 inspections, the last on Dec 24, 2024.

First inspection · 6.9%Latest · 100%
Construction started
June 14, 2022
Completion date registered with DLD
December 31, 2024
Site inspections
6
Units
127
Escrow bank
Commercial Bank Of Dubai(Psc)
DLD project no.
2417

Latest site photos

December 24, 2024

Progress over time

Progress over time
0%25%50%75%100%2024

Inspection history

  1. December 24, 2024

    6 months after the previous inspection

    +15.9%100%
  2. July 9, 2024

    4 months after the previous inspection

    +22.4%84.1%
  3. March 20, 2024

    6 months after the previous inspection

    +27.6%61.7%
  4. September 14, 2023

    4 months after the previous inspection

    +16.9%34.1%
  5. May 11, 2023

    4 months after the previous inspection

    +10.2%17.2%
  6. January 2, 2023

    First inspection

    6.9%

Thinking about Berkeley Place at Meydan by Ellington?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2417), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat