Belmont Residences at JVT Dubai

Construction progress

Belmont Residences at JVT Dubai construction updates

JVT · Ellington Properties Development L.L.C

CompletedLast site inspection August 20, 2026 · 3 months ago
100%complete

DLD first inspected the site on Apr 12, 2023 at 0% complete, and recorded it as finished after 8 inspections, the last on Aug 20, 2026.

First inspection · 0%Latest · 100%
Construction started
April 4, 2023
Site inspections
8
Units
69
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
2639

Latest site photos

August 20, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. August 20, 2026

    5 months after the previous inspection

    +10%100%
  2. March 26, 2026

    3 months after the previous inspection

    +12.7%90%
  3. December 11, 2025

    3 months after the previous inspection

    +14%77.3%
  4. September 4, 2025

    5 months after the previous inspection

    +20.7%63.3%
  5. April 10, 2025

    5 months after the previous inspection

    +20.4%42.6%
  6. November 20, 2024

    8 months after the previous inspection

    +19.7%22.2%
  7. April 4, 2024

    12 months after the previous inspection

    +2.5%2.5%
  8. April 12, 2023

    First inspection

    0%

Thinking about Belmont Residences at JVT Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2639), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.