Belle Reve at Jumeirah Village Circle Dubai

Construction progress

Belle Reve at Jumeirah Village Circle Dubai construction updates

JVC · Zimaya Properties L.L.C

Under constructionLast site inspection September 10, 2026 · 2 months ago
80.5%complete

When DLD first inspected the site on Apr 17, 2024, it was 0% complete. After 6 inspections it now stands at 80.5%.

That is about 2.8% more of the building completed each month on average.

First inspection · 0%Latest · 80.5%
Construction started
June 1, 2024
Completion date registered with DLD
August 31, 2026
Site inspections
6
Units
190
Buildings
2
Escrow bank
Mashreq Bank Psc
DLD project no.
3027

Latest site photos

September 10, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. September 10, 2026

    5 months after the previous inspection

    +20.1%80.5%
  2. April 13, 2026

    5 months after the previous inspection

    +15.4%60.4%
  3. November 6, 2025

    5 months after the previous inspection

    +18.5%45%
  4. June 12, 2025

    4 months after the previous inspection

    +14.4%26.5%
  5. January 27, 2025

    9 months after the previous inspection

    +12.1%12.1%
  6. April 17, 2024

    First inspection

    0%

Thinking about Belle Reve at Jumeirah Village Circle Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3027), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.