Beachgate By Address at Emaar Beachfront

Construction progress

Beachgate By Address at Emaar Beachfront construction updates

Emaar Beachfront · Emaar Development P.J.S.C.

CompletedLast site inspection September 21, 2026 · 2 months ago
100%complete

DLD first inspected the site on Feb 20, 2023 at 0% complete, and recorded it as finished after 11 inspections, the last on Sep 21, 2026.

First inspection · 0%Latest · 100%
Construction started
November 23, 2022
Completion date registered with DLD
December 31, 2026
Site inspections
11
Units
252
Escrow bank
Emirates Islamic Bank P.J.S.C.
DLD project no.
2430

Latest site photos

September 21, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. September 21, 2026

    3 months after the previous inspection

    +5%100%
  2. June 25, 2026

    5 months after the previous inspection

    +14.8%95%
  3. February 5, 2026

    4 months after the previous inspection

    +16.9%80.2%
  4. October 2, 2025

    3 months after the previous inspection

    +20.4%63.3%
  5. June 23, 2025

    5 months after the previous inspection

    +17.8%42.9%
  6. January 30, 2025

    5 months after the previous inspection

    +7.9%25.2%
  7. September 12, 2024

    6 months after the previous inspection

    +10.5%17.2%
  8. March 22, 2024

    6 months after the previous inspection

    +2.3%6.7%
  9. September 19, 2023

    4 months after the previous inspection

    +3.8%4.4%
  10. May 29, 2023

    3 months after the previous inspection

    +0.6%0.6%
  11. February 20, 2023

    First inspection

    0%

Thinking about Beachgate By Address at Emaar Beachfront?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2430), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat