Beach Walk Residence 3 at Dubai Islands

Construction progress

Beach Walk Residence 3 at Dubai Islands construction updates

Dubai Islands · Imtiaz Real Estate Investment & Development L.L.C

CompletedLast site inspection November 4, 2026 · 2 days ago
100%complete

DLD first inspected the site on Sep 9, 2024 at 0% complete, and recorded it as finished after 9 inspections, the last on Nov 4, 2026.

First inspection · 0%Latest · 100%
Construction started
September 15, 2024
Completion date registered with DLD
June 14, 2026
Site inspections
9
Units
82
Escrow bank
United Bank Limited (Management Office)
DLD project no.
3285

Latest site photos

November 4, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. November 4, 2026

    16 days after the previous inspection

    +2.7%100%
  2. October 19, 2026

    3 months after the previous inspection

    +15.3%97.3%
  3. July 20, 2026

    3 months after the previous inspection

    +14.8%82%
  4. April 24, 2026

    3 months after the previous inspection

    +9.2%67.2%
  5. January 9, 2026

    3 months after the previous inspection

    +21.8%58%
  6. October 10, 2025

    4 months after the previous inspection

    +9.5%36.2%
  7. June 12, 2025

    4 months after the previous inspection

    +19.5%26.7%
  8. February 4, 2025

    5 months after the previous inspection

    +7.2%7.2%
  9. September 9, 2024

    First inspection

    0%

Thinking about Beach Walk Residence 3 at Dubai Islands?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3285), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat