Construction progress
Dubai Islands · Imtiaz Ghd Real Estate Development L.L.C
DLD first inspected the site on Aug 15, 2024 at 0% complete, and recorded it as finished after 9 inspections, the last on Aug 6, 2026.
August 6, 2026
24 days after the previous inspection
2 months after the previous inspection
3 months after the previous inspection
3 months after the previous inspection
3 months after the previous inspection
2 months after the previous inspection
4 months after the previous inspection
5 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 3224), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.