Beach Walk Grand 2 by Imtiaz

Construction progress

Beach Walk Grand 2 by Imtiaz construction updates

Dubai Islands · Imtiaz Ghd Real Estate Development L.L.C

Under constructionLast site inspection September 14, 2026 · 2 months ago
23.5%complete

When DLD first inspected the site on May 1, 2025, it was 0% complete. After 6 inspections it now stands at 23.5%.

That is about 1.4% more of the building completed each month on average.

First inspection · 0%Latest · 23.5%
Construction started
July 1, 2025
Completion date registered with DLD
December 15, 2027
Site inspections
6
Units
108
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
3724

Latest site photos

September 14, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. September 14, 2026

    3 months after the previous inspection

    +6.1%23.5%
  2. June 23, 2026

    3 months after the previous inspection

    +9.1%17.5%
  3. March 23, 2026

    3 months after the previous inspection

    +3%8.4%
  4. December 23, 2025

    4 months after the previous inspection

    +5.2%5.4%
  5. September 4, 2025

    4 months after the previous inspection

    +0.2%0.2%
  6. May 1, 2025

    First inspection

    0%

Thinking about Beach Walk Grand 2 by Imtiaz?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3724), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.