Bayz 101 at Business Bay Dubai

Construction progress

Bayz 101 at Business Bay Dubai construction updates

Business Bay · Danube Properties Development L.L.C

Under constructionLast site inspection August 12, 2026 · 3 months ago
10%complete

When DLD first inspected the site on Jan 19, 2024, it was 0% complete. After 9 inspections it now stands at 10%.

That is about 0.3% more of the building completed each month on average.

First inspection · 0%Latest · 10%
Construction started
July 1, 2024
Site inspections
9
Units
1,346
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
2927

Latest site photos

August 12, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. August 12, 2026

    4 months after the previous inspection

    +0.7%10%
  2. April 16, 2026

    4 months after the previous inspection

    +1%9.3%
  3. December 23, 2025

    3 months after the previous inspection

    +2.8%8.3%
  4. September 29, 2025

    3 months after the previous inspection

    +0.4%5.5%
  5. July 3, 2025

    4 months after the previous inspection

    +1.6%5.1%
  6. March 4, 2025

    3 months after the previous inspection

    +3.1%3.5%
  7. December 6, 2024

    7 months after the previous inspection

    +0.2%0.4%
  8. April 23, 2024

    3 months after the previous inspection

    +0.2%0.2%
  9. January 19, 2024

    First inspection

    0%

Thinking about Bayz 101 at Business Bay Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2927), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.