Azizi Zain at Al Furjan, Dubai

Construction progress

Azizi Zain at Al Furjan, Dubai construction updates

Al Furjan · Azizi Developments L.L.C

Under constructionLast site inspection October 15, 2026 · 23 days ago
80.2%complete

When DLD first inspected the site on Oct 15, 2024, it was 0% complete. After 6 inspections it now stands at 80.2%.

That is about 3.3% more of the building completed each month on average.

First inspection · 0%Latest · 80.2%
Construction started
October 11, 2024
Completion date registered with DLD
October 11, 2027
Site inspections
6
Units
115
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
3335

Latest site photos

October 15, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 15, 2026

    4 months after the previous inspection

    +13.9%80.2%
  2. June 30, 2026

    5 months after the previous inspection

    +12.8%66.2%
  3. January 28, 2026

    3 months after the previous inspection

    +12.9%53.4%
  4. October 22, 2025

    5 months after the previous inspection

    +11.5%40.5%
  5. May 30, 2025

    7 months after the previous inspection

    +29%29%
  6. October 15, 2024

    First inspection

    0%

Thinking about Azizi Zain at Al Furjan, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3335), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.