Azizi Venice 14 at Dubai South

Construction progress

Azizi Venice 14 at Dubai South construction updates

Dubai South · Azizi Developments L.L.C

Under constructionLast site inspection June 22, 2026 · 5 months ago
30.3%complete

When DLD first inspected the site on May 6, 2024, it was 0% complete. After 5 inspections it now stands at 30.3%.

That is about 1.2% more of the building completed each month on average.

First inspection · 0%Latest · 30.3%
Construction started
May 2, 2024
Completion date registered with DLD
May 30, 2026
Site inspections
5
Units
3,438
Buildings
8
Escrow bank
Commercial Bank Of Dubai(Psc)
DLD project no.
3073

Latest site photos

June 22, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. June 22, 2026

    7 months after the previous inspection

    +16.4%30.3%
  2. November 14, 2025

    5 months after the previous inspection

    +4.9%13.8%
  3. June 20, 2025

    13 months after the previous inspection

    +8.9%8.9%
  4. May 6, 2024

    0 days after the previous inspection

    0%
  5. May 6, 2024

    First inspection

    0%

Thinking about Azizi Venice 14 at Dubai South?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3073), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.