Azizi Ruby at Jumeirah Village Circle

Construction progress

Azizi Ruby at Jumeirah Village Circle construction updates

JVC · Azizi Developments L.L.C

Under constructionLast site inspection March 25, 2026 · 7 months ago
3%complete

When DLD first inspected the site on Jan 27, 2025, it was 0% complete. After 2 inspections it now stands at 3%.

That is about 0.2% more of the building completed each month on average.

First inspection · 0%Latest · 3%
Construction started
January 23, 2025
Completion date registered with DLD
January 23, 2028
Site inspections
2
Units
264
Escrow bank
Al Ahli Bank Of Kuwait K S C P Dubai Branch
DLD project no.
3529

Latest site photos

March 25, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. March 25, 2026

    14 months after the previous inspection

    +3%3%
  2. January 27, 2025

    First inspection

    0%

Thinking about Azizi Ruby at Jumeirah Village Circle?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3529), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat