Azizi Riviera 69 at Meydan, Dubai

Construction progress

Azizi Riviera 69 at Meydan, Dubai construction updates

Meydan Dubai · Azizi Developments L.L.C

CompletedLast site inspection November 27, 2025 · 11 months ago
100%complete

DLD first inspected the site on Apr 30, 2024 at 33.6% complete, and recorded it as finished after 5 inspections, the last on Nov 27, 2025.

First inspection · 33.6%Latest · 100%
Construction started
March 15, 2024
Completion date registered with DLD
March 30, 2026
Site inspections
5
Units
123
Escrow bank
Commercial Bank Of Dubai(Psc)
DLD project no.
3012

Latest site photos

November 27, 2025

Progress over time

Progress over time
0%25%50%75%100%2025

Inspection history

  1. November 27, 2025

    36 days after the previous inspection

    +5%100%
  2. October 22, 2025

    4 months after the previous inspection

    +13.9%95%
  3. June 25, 2025

    5 months after the previous inspection

    +22.2%81.1%
  4. January 28, 2025

    9 months after the previous inspection

    +25.3%58.9%
  5. April 30, 2024

    First inspection

    33.6%

Thinking about Azizi Riviera 69 at Meydan, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3012), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.