Construction progress
Meydan Dubai · Azizi Developments L.L.C
DLD first inspected the site on Apr 30, 2024 at 33.6% complete, and recorded it as finished after 5 inspections, the last on Nov 27, 2025.
November 27, 2025
36 days after the previous inspection
4 months after the previous inspection
5 months after the previous inspection
9 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 3012), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.