Azizi Riviera 62

Construction progress

Azizi Riviera 62 construction updates

Meydan Dubai · Azizi Developments L.L.C

Under constructionLast site inspection July 30, 2026 · 3 months ago
90.8%complete

When DLD first inspected the site on Apr 5, 2025, it was 38.5% complete. After 4 inspections it now stands at 90.8%.

That is about 3.3% more of the building completed each month on average.

First inspection · 38.5%Latest · 90.8%
Construction started
March 13, 2025
Completion date registered with DLD
March 13, 2027
Site inspections
4
Units
112
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
3619

Latest site photos

July 30, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. July 30, 2026

    6 months after the previous inspection

    +20.6%90.8%
  2. January 21, 2026

    4 months after the previous inspection

    +13.6%70.2%
  3. September 12, 2025

    5 months after the previous inspection

    +18.1%56.6%
  4. April 5, 2025

    First inspection

    38.5%

Thinking about Azizi Riviera 62?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3619), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat