Azizi Riviera 61

Construction progress

Azizi Riviera 61 construction updates

Mohammad Bin Rashid City · Azizi Developments L.L.C

CompletedLast site inspection March 27, 2025 · 2 years ago
100%complete

DLD first inspected the site on Oct 31, 2023 at 37.2% complete, and recorded it as finished after 3 inspections, the last on Mar 27, 2025.

First inspection · 37.2%Latest · 100%
Construction started
October 12, 2023
Completion date registered with DLD
March 27, 2025
Site inspections
3
Units
240
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
2817

Latest site photos

March 27, 2025

Progress over time

Progress over time
0%25%50%75%100%20242025

Inspection history

  1. March 27, 2025

    9 months after the previous inspection

    +19.4%100%
  2. June 13, 2024

    7 months after the previous inspection

    +43.4%80.6%
  3. October 31, 2023

    First inspection

    37.2%

Thinking about Azizi Riviera 61?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2817), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.