Construction progress
Mohammad Bin Rashid City · Azizi Developments L.L.C
DLD first inspected the site on May 22, 2025 at 48.5% complete, and recorded it as finished after 3 inspections, the last on Aug 17, 2026.
August 17, 2026
7 months after the previous inspection
8 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 3737), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.