Construction progress
Mohammad Bin Rashid City · Azizi Developments L.L.C
DLD first inspected the site on Apr 8, 2025 at 53.5% complete, and recorded it as finished after 3 inspections, the last on Jan 19, 2026.
January 19, 2026
5 months after the previous inspection
4 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 3616), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.