Azizi Riviera 49 at Meydan, Dubai

Construction progress

Azizi Riviera 49 at Meydan, Dubai construction updates

Mohammad Bin Rashid City · Azizi Developments L.L.C

Under constructionLast site inspection August 7, 2026 · 3 months ago
54.4%complete

When DLD first inspected the site on Apr 8, 2025, it was 28.7% complete. After 4 inspections it now stands at 54.4%.

That is about 1.6% more of the building completed each month on average.

First inspection · 28.7%Latest · 54.4%
Construction started
March 13, 2025
Completion date registered with DLD
March 13, 2027
Site inspections
4
Units
234
Escrow bank
Commercial Bank Of Dubai(Psc)
DLD project no.
3613

Latest site photos

August 7, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. August 7, 2026

    7 months after the previous inspection

    +9%54.4%
  2. January 19, 2026

    5 months after the previous inspection

    +11.4%45.4%
  3. August 18, 2025

    4 months after the previous inspection

    +5.3%34%
  4. April 8, 2025

    First inspection

    28.7%

Thinking about Azizi Riviera 49 at Meydan, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3613), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.