Azizi Neila at Al Furjan, Dubai

Construction progress

Azizi Neila at Al Furjan, Dubai construction updates

Al Furjan · Azizi Developments L.L.C

Under constructionLast site inspection October 5, 2026 · 33 days ago
38.5%complete

When DLD first inspected the site on Aug 20, 2024, it was 0% complete. After 5 inspections it now stands at 38.5%.

That is about 1.5% more of the building completed each month on average.

First inspection · 0%Latest · 38.5%
Construction started
July 23, 2024
Completion date registered with DLD
July 30, 2027
Site inspections
5
Units
274
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
3203

Latest site photos

October 5, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 5, 2026

    6 months after the previous inspection

    +21.5%38.5%
  2. April 13, 2026

    4 months after the previous inspection

    +4.9%17.1%
  3. December 9, 2025

    0 days after the previous inspection

    12.2%
  4. December 9, 2025

    16 months after the previous inspection

    +12.2%12.2%
  5. August 20, 2024

    First inspection

    0%

Thinking about Azizi Neila at Al Furjan, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3203), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.