Azizi Lina at Downtown Jebel Ali

Construction progress

Azizi Lina at Downtown Jebel Ali construction updates

Downtown Jebel ALi · Azizi Developments L.L.C

Under constructionLast site inspection March 18, 2026 · 8 months ago
2%complete

When DLD first inspected the site on Oct 14, 2025, it was 0% complete. After 2 inspections it now stands at 2%.

That is about 0.4% more of the building completed each month on average.

First inspection · 0%Latest · 2%
Construction started
February 3, 2026
Completion date registered with DLD
September 30, 2028
Site inspections
2
Units
242
Escrow bank
Ajman Bank /P.J.S.C
DLD project no.
4141

Latest site photos

March 18, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. March 18, 2026

    5 months after the previous inspection

    +2%2%
  2. October 14, 2025

    First inspection

    0%

Thinking about Azizi Lina at Downtown Jebel Ali?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 4141), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.