Azizi Leily at Al Jaddaf, Dubai

Construction progress

Azizi Leily at Al Jaddaf, Dubai construction updates

Al Jaddaf · Azizi Developments L.L.C

Under constructionLast site inspection March 24, 2026 · 7 months ago
2%complete

When DLD first inspected the site on Nov 18, 2025, it was 0% complete. After 2 inspections it now stands at 2%.

That is about 0.5% more of the building completed each month on average.

First inspection · 0%Latest · 2%
Construction started
March 4, 2026
Completion date registered with DLD
September 30, 2028
Site inspections
2
Units
272
Escrow bank
Ajman Bank /P.J.S.C
DLD project no.
4233

Latest site photos

March 24, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. March 24, 2026

    4 months after the previous inspection

    +2%2%
  2. November 18, 2025

    First inspection

    0%

Thinking about Azizi Leily at Al Jaddaf, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 4233), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.