Azizi Greenfield at Meydan City

Construction progress

Azizi Greenfield at Meydan City construction updates

Meydan Dubai · Azizi Developments L.L.C

CompletedLast site inspection March 8, 2024 · 3 years ago
100%complete

DLD first inspected the site on Feb 28, 2021 at 1% complete, and recorded it as finished after 6 inspections, the last on Mar 8, 2024.

First inspection · 1%Latest · 100%
Construction started
February 1, 2018
Completion date registered with DLD
March 8, 2024
Site inspections
6
Units
102
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
2035

Latest site photos

March 8, 2024

Progress over time

Progress over time
0%25%50%75%100%202220232024

Inspection history

  1. March 8, 2024

    11 months after the previous inspection

    +59.3%100%
  2. March 29, 2023

    5 months after the previous inspection

    +8.4%40.7%
  3. October 26, 2022

    7 months after the previous inspection

    +2%32.3%
  4. April 4, 2022

    6 months after the previous inspection

    +13.1%30.4%
  5. October 10, 2021

    7 months after the previous inspection

    +16.2%17.2%
  6. February 28, 2021

    First inspection

    1%

Thinking about Azizi Greenfield at Meydan City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2035), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.