Avant Garde Residences at JVC

Construction progress

Avant Garde Residences at JVC construction updates

JVC · Skyline Builders Real Estate L.L.C

CompletedLast site inspection August 24, 2026 · 2 months ago
100%complete

DLD first inspected the site on Oct 11, 2023 at 0% complete, and recorded it as finished after 10 inspections, the last on Aug 24, 2026.

First inspection · 0%Latest · 100%
Construction started
November 14, 2023
Site inspections
10
Units
174
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
2798

Latest site photos

August 24, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. August 24, 2026

    2 months after the previous inspection

    +3.6%100%
  2. July 2, 2026

    3 months after the previous inspection

    +10%96.4%
  3. March 31, 2026

    3 months after the previous inspection

    +16.3%86.3%
  4. December 30, 2025

    3 months after the previous inspection

    +11%70.1%
  5. September 19, 2025

    3 months after the previous inspection

    +8.3%59.1%
  6. June 24, 2025

    4 months after the previous inspection

    +21.1%50.8%
  7. February 13, 2025

    3 months after the previous inspection

    +14%29.6%
  8. October 30, 2024

    5 months after the previous inspection

    +12%15.7%
  9. June 10, 2024

    8 months after the previous inspection

    +3.7%3.7%
  10. October 11, 2023

    First inspection

    0%

Thinking about Avant Garde Residences at JVC?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2798), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.