Aura at Jumeirah Village Circle Dubai

Construction progress

Aura at Jumeirah Village Circle Dubai construction updates

JVC · Grovy Homes Real Estate Development L.L.C

CompletedLast site inspection May 30, 2025 · 17 months ago
100%complete

DLD first inspected the site on Nov 21, 2022 at 3.8% complete, and recorded it as finished after 7 inspections, the last on May 30, 2025.

First inspection · 3.8%Latest · 100%
Construction started
May 17, 2022
Completion date registered with DLD
August 11, 2024
Site inspections
7
Units
151
Escrow bank
Bank Of Baroda
DLD project no.
2440

Latest site photos

May 30, 2025

Progress over time

Progress over time
0%25%50%75%100%202320242025

Inspection history

  1. May 30, 2025

    12 months after the previous inspection

    +29.9%100%
  2. June 4, 2024

    3 months after the previous inspection

    +15.6%70.1%
  3. March 12, 2024

    4 months after the previous inspection

    +24.4%54.5%
  4. October 30, 2023

    4 months after the previous inspection

    +13.3%30.2%
  5. July 14, 2023

    3 months after the previous inspection

    +7.4%16.8%
  6. April 4, 2023

    4 months after the previous inspection

    +5.7%9.4%
  7. November 21, 2022

    First inspection

    3.8%

Thinking about Aura at Jumeirah Village Circle Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2440), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.