Aspirz by Danube

Construction progress

Aspirz by Danube construction updates

Sports City Dubai · Danube Properties Development L.L.C

Under constructionLast site inspection October 28, 2026 · 10 days ago
8.6%complete

When DLD first inspected the site on Sep 4, 2025, it was 0% complete. After 4 inspections it now stands at 8.6%.

That is about 0.6% more of the building completed each month on average.

First inspection · 0%Latest · 8.6%
Construction started
November 1, 2025
Completion date registered with DLD
December 31, 2028
Site inspections
4
Units
706
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
3838

Latest site photos

October 28, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. October 28, 2026

    3 months after the previous inspection

    +3.5%8.6%
  2. July 30, 2026

    4 months after the previous inspection

    +4%5.1%
  3. April 6, 2026

    7 months after the previous inspection

    +1.1%1.1%
  4. September 4, 2025

    First inspection

    0%

Thinking about Aspirz by Danube?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3838), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.