Aquora by Casa Vista

Construction progress

Aquora by Casa Vista construction updates

Dubai Islands · Casa Vista Development L.L.C

Under constructionLast site inspection July 21, 2026 · 4 months ago
2.7%complete

When DLD first inspected the site on Aug 26, 2025, it was 0% complete. After 2 inspections it now stands at 2.7%.

That is about 0.2% more of the building completed each month on average.

First inspection · 0%Latest · 2.7%
Construction started
October 11, 2025
Completion date registered with DLD
October 11, 2028
Site inspections
2
Units
111
Escrow bank
United Bank Limited (Management Office)
DLD project no.
4014

Latest site photos

July 21, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. July 21, 2026

    11 months after the previous inspection

    +2.7%2.7%
  2. August 26, 2025

    First inspection

    0%

Thinking about Aquora by Casa Vista?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 4014), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat