Amaal 8 at Mohammed Bin Rashid City

Construction progress

Amaal 8 at Mohammed Bin Rashid City construction updates

Mohammad Bin Rashid City · Amaal Emirates L.L.C

Under constructionLast site inspection October 28, 2026 · 10 days ago
11.3%complete

When DLD first inspected the site on Apr 5, 2024, it was 0% complete. After 5 inspections it now stands at 11.3%.

That is about 0.4% more of the building completed each month on average.

First inspection · 0%Latest · 11.3%
Construction started
March 7, 2024
Completion date registered with DLD
December 31, 2028
Site inspections
5
Units
533
Escrow bank
Commercial Bank Of Dubai(Psc)
DLD project no.
3004

Latest site photos

October 28, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 28, 2026

    3 months after the previous inspection

    +4.2%11.3%
  2. July 16, 2026

    4 months after the previous inspection

    +1.4%7%
  3. March 24, 2026

    8 months after the previous inspection

    +4.1%5.7%
  4. July 28, 2025

    16 months after the previous inspection

    +1.6%1.6%
  5. April 5, 2024

    First inspection

    0%

Thinking about Amaal 8 at Mohammed Bin Rashid City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3004), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.