Alta View Skyhomes

Construction progress

Alta View Skyhomes construction updates

JVC · Object One Real Estate Development L.L.C

Under constructionLast site inspection September 16, 2026 · 2 months ago
5.8%complete

When DLD first inspected the site on Jun 17, 2025, it was 0% complete. After 4 inspections it now stands at 5.8%.

That is about 0.4% more of the building completed each month on average.

First inspection · 0%Latest · 5.8%
Construction started
August 1, 2025
Completion date registered with DLD
June 30, 2029
Site inspections
4
Units
507
Escrow bank
Abu Dhabi Islamic Bank
DLD project no.
3842

Latest site photos

September 16, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. September 16, 2026

    3 months after the previous inspection

    +1.8%5.8%
  2. June 4, 2026

    3 months after the previous inspection

    +4%4.1%
  3. February 19, 2026

    8 months after the previous inspection

    +0.1%0.1%
  4. June 17, 2025

    First inspection

    0%

Thinking about Alta View Skyhomes?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3842), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat