Albero by ORO24

Construction progress

Albero by ORO24 construction updates

Dubailand · Oro24 Real Estate Development L.L.C

Under constructionLast site inspection September 10, 2026 · 2 months ago
44.8%complete

When DLD first inspected the site on Nov 15, 2023, it was 0% complete. After 6 inspections it now stands at 44.8%.

That is about 1.3% more of the building completed each month on average.

First inspection · 0%Latest · 44.8%
Construction started
November 30, 2023
Site inspections
6
Units
192
Escrow bank
Mashreq Bank Psc
DLD project no.
2848

Latest site photos

September 10, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. September 10, 2026

    5 months after the previous inspection

    +16%44.8%
  2. March 27, 2026

    4 months after the previous inspection

    +5.7%28.8%
  3. December 10, 2025

    3 months after the previous inspection

    +5.1%23.1%
  4. September 19, 2025

    3 months after the previous inspection

    +8.3%17.9%
  5. June 11, 2025

    19 months after the previous inspection

    +9.6%9.6%
  6. November 15, 2023

    First inspection

    0%

Thinking about Albero by ORO24?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2848), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.