Akala Hotels and Residences

Construction progress

Akala Hotels and Residences construction updates

Zabeel Park · Arada Developments L.L.C S.O.C

Under constructionLast site inspection October 13, 2026 · 25 days ago
1.9%complete

When DLD first inspected the site on May 6, 2025, it was 0% complete. After 4 inspections it now stands at 1.9%.

That is about 0.1% more of the building completed each month on average.

First inspection · 0%Latest · 1.9%
Construction started
May 1, 2026
Completion date registered with DLD
October 31, 2029
Site inspections
4
Units
546
Buildings
2
Escrow bank
Commercial Bank Of Dubai(Psc)
DLD project no.
3745

Latest site photos

October 13, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. October 13, 2026

    3 months after the previous inspection

    +1.8%1.9%
  2. July 9, 2026

    4 months after the previous inspection

    +0.1%0.1%
  3. March 24, 2026

    11 months after the previous inspection

    0%
  4. May 6, 2025

    First inspection

    0%

Thinking about Akala Hotels and Residences?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3745), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.