AG Central at Dubailand Residence Complex

Construction progress

AG Central at Dubailand Residence Complex construction updates

Dubailand · Ag Properties L.L.C

Under constructionLast site inspection September 17, 2026 · 2 months ago
58.7%complete

When DLD first inspected the site on Sep 18, 2023, it was 2.3% complete. After 6 inspections it now stands at 58.7%.

That is about 1.6% more of the building completed each month on average.

First inspection · 2.3%Latest · 58.7%
Construction started
October 31, 2023
Completion date registered with DLD
October 31, 2026
Site inspections
6
Units
96
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2422

Latest site photos

September 17, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. September 17, 2026

    7 months after the previous inspection

    +7.8%58.7%
  2. February 9, 2026

    4 months after the previous inspection

    +2.5%50.8%
  3. October 13, 2025

    7 months after the previous inspection

    +10.4%48.3%
  4. March 21, 2025

    5 months after the previous inspection

    +14.4%38%
  5. October 16, 2024

    13 months after the previous inspection

    +21.2%23.6%
  6. September 18, 2023

    First inspection

    2.3%

Thinking about AG Central at Dubailand Residence Complex?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2422), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat