AG 9ine at Dubailand

Construction progress

AG 9ine at Dubailand construction updates

Dubailand · Ag Properties L.L.C

Under constructionLast site inspection July 30, 2026 · 3 months ago
38.4%complete

When DLD first inspected the site on Jan 11, 2024, it was 0% complete. After 4 inspections it now stands at 38.4%.

That is about 1.3% more of the building completed each month on average.

First inspection · 0%Latest · 38.4%
Construction started
January 31, 2024
Site inspections
4
Units
260
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2847

Latest site photos

July 30, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. July 30, 2026

    6 months after the previous inspection

    +10.1%38.4%
  2. February 12, 2026

    11 months after the previous inspection

    +13.7%28.3%
  3. March 21, 2025

    14 months after the previous inspection

    +14.7%14.7%
  4. January 11, 2024

    First inspection

    0%

Thinking about AG 9ine at Dubailand?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2847), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.