AG 7even at Dubai Land Residence Complex

Construction progress

AG 7even at Dubai Land Residence Complex construction updates

Dubai Land Residence Complex (DLRC) · Ag Properties L.L.C

Under constructionLast site inspection June 18, 2026 · 5 months ago
93.7%complete

When DLD first inspected the site on Mar 27, 2023, it was 1.1% complete. After 8 inspections it now stands at 93.7%.

That is about 2.4% more of the building completed each month on average.

First inspection · 1.1%Latest · 93.7%
Construction started
March 31, 2023
Completion date registered with DLD
March 31, 2027
Site inspections
8
Units
234
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2605

Latest site photos

June 18, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. June 18, 2026

    4 months after the previous inspection

    +8.6%93.7%
  2. February 12, 2026

    4 months after the previous inspection

    +21.2%85.1%
  3. October 9, 2025

    6 months after the previous inspection

    +12.1%63.8%
  4. April 14, 2025

    5 months after the previous inspection

    +11.3%51.8%
  5. November 7, 2024

    8 months after the previous inspection

    +22.7%40.4%
  6. March 15, 2024

    4 months after the previous inspection

    +3.5%17.7%
  7. November 13, 2023

    8 months after the previous inspection

    +13%14.2%
  8. March 27, 2023

    First inspection

    1.1%

Thinking about AG 7even at Dubai Land Residence Complex?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2605), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.