Adhara Star at Arjan Dubai

Construction progress

Adhara Star at Arjan Dubai construction updates

Arjan Dubai · Acube Real Estate Development L L C

CompletedLast site inspection October 16, 2025 · 13 months ago
100%complete

DLD first inspected the site on Mar 20, 2023 at 0% complete, and recorded it as finished after 8 inspections, the last on Oct 16, 2025.

First inspection · 0%Latest · 100%
Construction started
May 15, 2023
Completion date registered with DLD
March 10, 2025
Site inspections
8
Units
115
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2606

Latest site photos

October 16, 2025

Progress over time

Progress over time
0%25%50%75%100%20242025

Inspection history

  1. October 16, 2025

    4 months after the previous inspection

    +5.1%100%
  2. July 1, 2025

    5 months after the previous inspection

    +24.5%94.9%
  3. February 10, 2025

    3 months after the previous inspection

    +25.3%70.3%
  4. November 1, 2024

    2 months after the previous inspection

    +14.8%45%
  5. August 21, 2024

    3 months after the previous inspection

    +14.8%30.2%
  6. May 9, 2024

    5 months after the previous inspection

    +7.7%15.4%
  7. December 11, 2023

    9 months after the previous inspection

    +7.7%7.7%
  8. March 20, 2023

    First inspection

    0%

Thinking about Adhara Star at Arjan Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2606), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.