Construction progress

7 Park Central at JVC Dubai construction updates

JVC · Meteora Real Estate Development L.L.C

Under constructionLast site inspection February 14, 2025 · 2 years ago
90.2%complete

When DLD first inspected the site on Jan 23, 2023, it was 27.2% complete. After 5 inspections it now stands at 90.2%.

That is about 2.5% more of the building completed each month on average.

First inspection · 27.2%Latest · 90.2%
Construction started
March 13, 2023
Completion date registered with DLD
April 30, 2025
Site inspections
5
Units
121
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
2557

Latest site photos

February 14, 2025

Progress over time

Progress over time
0%25%50%75%100%20242025

Inspection history

  1. February 14, 2025

    9 months after the previous inspection

    +20%90.2%
  2. May 8, 2024

    6 months after the previous inspection

    +18.9%70.2%
  3. November 16, 2023

    4 months after the previous inspection

    +7.6%51.3%
  4. July 20, 2023

    6 months after the previous inspection

    +16.5%43.7%
  5. January 23, 2023

    First inspection

    27.2%

Thinking about 7 Park Central at JVC Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2557), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.