Construction progress
Arjan Dubai · Tabeer Real Estate Development L.L.C
DLD first inspected the site on Nov 16, 2023 at 5% complete, and recorded it as finished after 10 inspections, the last on May 7, 2026.
May 7, 2026
6 months after the previous inspection
8 months after the previous inspection
0 days after the previous inspection
2 months after the previous inspection
3 months after the previous inspection
6 days after the previous inspection
3 months after the previous inspection
34 days after the previous inspection
6 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 2831), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.