360 Riverside Crescent at Sobha Hartland 2

Construction progress

360 Riverside Crescent at Sobha Hartland 2 construction updates

Sobha Hartland 2 · Sobha L.L.C

Under constructionLast site inspection September 16, 2026 · 2 months ago
50.7%complete

When DLD first inspected the site on May 14, 2024, it was 0% complete. After 8 inspections it now stands at 50.7%.

That is about 1.8% more of the building completed each month on average.

First inspection · 0%Latest · 50.7%
Construction started
May 10, 2024
Site inspections
8
Units
910
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
3079

Latest site photos

September 16, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. September 16, 2026

    3 months after the previous inspection

    +7.8%50.7%
  2. June 16, 2026

    3 months after the previous inspection

    +6.7%42.9%
  3. March 26, 2026

    4 months after the previous inspection

    +9.1%36.1%
  4. November 20, 2025

    0 days after the previous inspection

    27%
  5. November 20, 2025

    6 months after the previous inspection

    +7%27%
  6. May 9, 2025

    5 months after the previous inspection

    +9.7%20%
  7. December 23, 2024

    7 months after the previous inspection

    +10.3%10.3%
  8. May 14, 2024

    First inspection

    0%

Thinking about 360 Riverside Crescent at Sobha Hartland 2?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3079), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.