Construction progress

330 Riverside Crescent at Sobha Hartland 2 construction updates

Sobha Hartland 2 · Sobha L.L.C

Under constructionLast site inspection October 12, 2026 · 26 days ago
67.8%complete

When DLD first inspected the site on Oct 12, 2023, it was 0% complete. After 10 inspections it now stands at 67.8%.

That is about 1.9% more of the building completed each month on average.

First inspection · 0%Latest · 67.8%
Construction started
October 12, 2023
Site inspections
10
Units
767
Escrow bank
Emirates Islamic Bank P.J.S.C.
DLD project no.
2788

Latest site photos

October 12, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. October 12, 2026

    3 months after the previous inspection

    +7.4%67.8%
  2. July 9, 2026

    4 months after the previous inspection

    +11.5%60.4%
  3. March 18, 2026

    4 months after the previous inspection

    +11.1%48.9%
  4. November 10, 2025

    3 months after the previous inspection

    +6.8%37.8%
  5. July 28, 2025

    3 months after the previous inspection

    +7.6%31%
  6. April 16, 2025

    3 months after the previous inspection

    +3.3%23.4%
  7. January 7, 2025

    4 months after the previous inspection

    +4.4%20.1%
  8. September 17, 2024

    4 months after the previous inspection

    +8%15.7%
  9. May 23, 2024

    7 months after the previous inspection

    +7.7%7.7%
  10. October 12, 2023

    First inspection

    0%

Thinking about 330 Riverside Crescent at Sobha Hartland 2?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2788), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.