320 Riverside Crescent at Sobha Hartland 2

Construction progress

320 Riverside Crescent at Sobha Hartland 2 construction updates

Sobha Hartland 2 · Sobha L.L.C

Under constructionLast site inspection August 24, 2026 · 2 months ago
56.7%complete

When DLD first inspected the site on May 7, 2024, it was 0% complete. After 8 inspections it now stands at 56.7%.

That is about 2.1% more of the building completed each month on average.

First inspection · 0%Latest · 56.7%
Construction started
May 10, 2024
Site inspections
8
Units
638
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
3088

Latest site photos

August 24, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. August 24, 2026

    3 months after the previous inspection

    +6.5%56.7%
  2. May 22, 2026

    3 months after the previous inspection

    +13.1%50.2%
  3. February 9, 2026

    5 months after the previous inspection

    +6.2%37.1%
  4. September 15, 2025

    4 months after the previous inspection

    +10.8%30.9%
  5. May 9, 2025

    3 months after the previous inspection

    +3.1%20.2%
  6. February 11, 2025

    3 months after the previous inspection

    +3.7%17.1%
  7. November 5, 2024

    6 months after the previous inspection

    +13.4%13.4%
  8. May 7, 2024

    First inspection

    0%

Thinking about 320 Riverside Crescent at Sobha Hartland 2?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3088), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.