15 Cascade at Dubai Motor City

Construction progress

15 Cascade at Dubai Motor City construction updates

Motor City Dubai · Iman Developers L.L.C

Under constructionLast site inspection July 2, 2026 · 4 months ago
5.5%complete

When DLD first inspected the site on Jan 28, 2025, it was 0% complete. After 3 inspections it now stands at 5.5%.

That is about 0.3% more of the building completed each month on average.

First inspection · 0%Latest · 5.5%
Construction started
March 30, 2025
Completion date registered with DLD
September 30, 2028
Site inspections
3
Units
442
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
3528

Latest site photos

July 2, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. July 2, 2026

    6 months after the previous inspection

    +4%5.5%
  2. December 25, 2025

    11 months after the previous inspection

    +1.5%1.5%
  3. January 28, 2025

    First inspection

    0%

Thinking about 15 Cascade at Dubai Motor City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3528), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.